In a landmark achievement for Imo State, Governor Hope Uzodimma has successfully delivered a state-of-the-art 63MVA, 132KV/33KV Mobitra Substation, marking a transformative step in the state’s energy landscape. This cutting-edge facility located at Obinze, was secured by the Governor through the Federal Government’s Presidential Power Initiative Scheme. The project will increase electricity supply in Owerri and its environs, providing approximately 50 megawatts of additional power capacity to homes, businesses, and industries.





The Mobitra Substation, designed to handle 63 megavolt-amperes (MVA) of electrical power, will convert high-voltage 132KV electricity into a more usable 33KV for local distribution. This critical infrastructure will bridge the gap between the national transmission grid and local networks, ensuring seamless power delivery to communities in and around the Imo capital city.


Governor Uzodimma’s administration has also facilitated other significant power projects, including the Energizing Education Power Program, which will install an 82-megawatt solar hybrid power plant at the Federal University of Technology, Owerri (FUTO). These initiatives underscore the government’s commitment to addressing Imo State’s longstanding power challenges.



Honourable Commissioner for Power and Electrification, Engr. Nwabueze Oguchienti, highlighted additional projects underway as part of the state’s comprehensive energy development plan. These will include:  

- A new 330KV transmission line from Egbema to Owerri.  

- A 330KV transmission line from Alaoji to Owerri.

- Installation of two 150MVA, 330KV transformers at Egbu for bulk power distribution.  

- Two 60MVA/132KV transformers at Egbu and two 60MVA, 132KV/33KV transformers at Orlu.  

- Construction of a 132KV transmission line from Egbu to Orlu to connect the transformers.  

- Expansion of the 33KV distribution network into New Owerri and a 33KV line from Orlu to Imo Polytechnic, Omuma, linked to a 15MVA injection substation.  


Engr. Oguchienti emphasized that these projects are part of the government’s broader strategy to enhance electricity transmission and distribution across Imo State. 



He also noted that the Obinze community’s traditional ruler and president general were duly consulted to ensure community buy-in for the Mobitra Substation project.


With Okigwe urban slated to benefit from the second phase of the Mobitra Substation, Governor Uzodimma’s administration is poised to deliver a brighter, more energized future for Imo State, fostering economic growth and improving the quality of life for its residents.